Traffic restrictions ahead in highway project

SIERRA VISTA — Work will continue this week on the Highway 92 widening project between Carr Canyon Road and Hunter Canyon.

Arizona Department of Transportation crews are scheduled to work Monday through Friday.

There will be traffic restrictions are East La Paloma Lane and Highway 92 between 6:30 a.m. and 5 p.m. on Monday, ADOT said.

There also will be restrictions on South Bamboo Circle and Highway 82 from 6:30 a.m. to 5 p.m. on Tuesday.

Flaggers will be at the site both days to direct traffic through the construction area.

The crews also will:

• Continue work on box culvert extensions and excavation at the culvert outlets on the west and east sides of the highway.

• Continue to work on the embankment subgrade along the east side of the roadway, from Hereford Road north to the end of the project.

• Continue to construct the protection structures for the Tombstone water line throughout the project.

ADOT says drivers should watch traffic control signs.

For information, call Susan Parcells at (520) 327-6077.

ON THE NET

• Department of Transportation: www.dot.state.az.us/